City Of Davis Emergency Waterline Repair
The City of Davis’s surface water transmission line was compromised by a directional drill operation on Wednesday, March 23rd at 10:45 a.m. Without this line the City is cut off from their water supply, operating at a limited capacity on their groundwater wells only.
Details
OWNER: City of Davis
LOCATION: Davis, California
GENERAL CONTRACTOR: McGuire and Hester
DURATION: 24 Hours
COMPLETION: March 2022
Type of Project
Public Utilities
Services We Provided
Desription
Once our emergency response team received the call, our crew was on-site coordinationg and staffing all items needed for next steps by 3:30 pm. This consisted of a crew of 7 laborers and operators on site, a 65k lb excavator, a 938 loader, super dump, trench shields, hydraulic jacks, steel plates, dewatering pumps and a rig welder with steel to make the repair ready to go.
After a quick walk through with the crew, we broke ground exposing the line and dewatering before 4pm. By 7pm our crew had the pipe fully exposed and was able to determine the severity of the hit. As the day got late, the crew added light towers to the jobsite and dewatered for 3 hours until they were able to cut and patch the pipe with a welded steel buttstrap. The operation was completed with the pipe under chlorination before midnight the same day. The next morning we assisted the city in pressure testing the line and putting it back in service within 24 hours of the initial hit.

Worksite Images
More Projects With Same Services
More Projects In Similar Markets
City of Davis Sewer Main Emergency Project
Natomas Reach A Levee Improvements
Woodland Davis Clean Water Agency Water Main Repair
Placerville Lennar Homes Microtunneling Project
Oakland Zoo Emergency Project
Hale Creek Pilot Enhancement Project
City of Davis Sewer Lift Station #3
City Of Davis Emergency Waterline Repair
City of Davis 66-Inch Influent Sewer Slip-lining
Presidio Tunnel Tops Landscape
Sacramento Water Meter Retrofits
City of Folsom Willow Hill Pipeline Rehabilitation Phase 2
Sacramento 9th Street Sewer Improvement
Newark Twin Force Main Relocation
Olympic Pump Station & Force Main
Noble Gulch Trunkline
City of Palo Alto Reclaimed Water Pipeline
Storm Drain Outfall & Treatment Pond Pacific Commons
Alameda County Water District Large Diameter Pipeline
Livermore-Amador Valley Water Management Agency Wetland Restoration
DSRSD Recyled Water Expansion Phase I
Moraga Sinkhole & Storm Drain

City of Davis L St. Improvements
Mather Airport