Sacramento 9th Street Sewer Improvement
The 9th Street Sewer Improvement project in downtown Sacramento was developed to allow additional storm drain and sewer capacities in the heart of downtown Sacramento. The project consisted of installing approximately 2,200 linear feet of 60- inch RCP combined sewer and storm drain system.
Details
OWNER: City of Sacramento
LOCATION: Downtown Sacramento, California
Type of Project
Public Utilities
Services We Provided
Desription
McGuire and Hester faced some unique challenges while constructing and successfully completing this project. The existing 24-inch combined sewer system had to remain active throughout the entire project. To make this happen, several bypass systems were simultaneously running. Half of this project was done with a 74-inch tunnel boring machine. McGuire and Hester dug two jacking pits and the average invert of the tunnel boring pipe was 20 ft below the surface. A few of the challenges faced with this type of boring included the potential for groundwater, existing underground fiber utilities, and a live sewer system just feet above the tunnel boring machine.
The second half of this project was installing the 60- inch RCP with open cut bell and spigot pipe. The dense consortium of new old and unknown utilities was difficult in a downtown setting. It took the experience and creativity of our field personnel to adapt with multiple shoring techniques and consulting with the engineer for redesign options to allow the system to function properly.
Upon completion of the installation of the underground utilities the City then asked McGuire and Hester to repave the entire street with a slurry seal and new striping format to match current city standards.

Worksite Images
More Projects With Same Services
More Projects In Similar Markets
City of Davis Sewer Main Emergency Project
Natomas Reach A Levee Improvements
Woodland Davis Clean Water Agency Water Main Repair
Placerville Lennar Homes Microtunneling Project
Oakland Zoo Emergency Project
Hale Creek Pilot Enhancement Project
City of Davis Sewer Lift Station #3
City Of Davis Emergency Waterline Repair
City of Davis 66-Inch Influent Sewer Slip-lining
Presidio Tunnel Tops Landscape
Sacramento Water Meter Retrofits
City of Folsom Willow Hill Pipeline Rehabilitation Phase 2
Sacramento 9th Street Sewer Improvement
Newark Twin Force Main Relocation
Olympic Pump Station & Force Main
Noble Gulch Trunkline
City of Palo Alto Reclaimed Water Pipeline
Storm Drain Outfall & Treatment Pond Pacific Commons
Alameda County Water District Large Diameter Pipeline
Livermore-Amador Valley Water Management Agency Wetland Restoration
DSRSD Recyled Water Expansion Phase I
Moraga Sinkhole & Storm Drain

San Francisco 5th and Bryant
City of Alameda Jean Sweeney Park