
City of Folsom Willow Hill Pipeline Rehabilitation Phase 2
Sliplining rehabilitation of approximately 2400 lf of existing 48-inch & 42-inch RCP with 28-inch HDPE, and 1 mile of existing 30-inch RCP with 24-inch Fusible PVC.
Details
OWNER: City of Folsom
LOCATION: Folsom, California
CONTRACT VALUE: $3.8 MM
COMPLETION: June 2017
Type of Project
Public Utilities
Services We Provided
Desription
Installation of approximately 3,000 lf of new 24-inch diameter restrained DIP alignment along Randall Drive, Riley Street, and through Livermore Park via open cut methods. Installation of line valves, pig launching station, abandonment of existing pipelines and appurtenances and other miscellaneous improvements.
Worksite Images
More Projects With Same Services
Prev
1
2
3
4
5
6
7
8
9
10
11
12
13
Next
More Projects In Similar Markets

Sacramento Water Meter Retrofits
San Francisco 5th and Bryant
