City of Folsom Willow Hill Pipeline Rehabilitation Phase 2

Sliplining rehabilitation of approximately 2400 lf of existing 48-inch & 42-inch RCP with 28-inch HDPE, and 1 mile of existing 30-inch RCP with 24-inch Fusible PVC.

Details

OWNER: City of Folsom

LOCATION: Folsom, California

CONTRACT VALUE: $3.8 MM

COMPLETION: June 2017

Type of Project

Public Utilities

Services We Provided

Desription

Installation of approximately 3,000 lf of new 24-inch diameter restrained DIP alignment along Randall Drive, Riley Street, and through Livermore Park via open cut methods. Installation of line valves, pig launching station, abandonment of existing pipelines and appurtenances and other miscellaneous improvements.